DODGE HANGERS SHEATHING
NO DROP SYSTEM®
To install the starter row of exterior sheathing so that it is flush or even with the bottom of the mudsill, having no drop over the top of the foundation wall, use the Dodge Hanger Corner® ‘0’ (DHC0) along with the Dodge Hanger Bottom® (DHB).
Select the DHC0 and the DHB with a saddle width that matches the thickness of the sheathing material to be installed.
👉🏻 You will need one DHC0 for each outside corner.
👉🏻 Bend the top tab of the DHC0 over and place on mudsill at each corner. If mudsill is larger than 1.5”, do not bend the top tab over, but attach directly to the side of the mudsill.
👉🏻 Lightly hammer the stab tab on the DHC0 to help hold it in place on the mudsill.
👉🏻 Fasten the DHC0 to the mudsill with Approved Fasteners*.5. Starting with a corner, it is recommended you attach the DHB on a 1’ by 3’ pattern around the mud sill plate, after establishing the layout of the product being used. You should place a DHB no more than 6” in from each joint/seam.6. For vertically installed sheathing (4’ x 8’, 9’, 10’, 12’) it is recommended you use (2) DHB’s per sheet of sheathing material.
👉🏻 Insert the bottom tab of the DHB between the mudsill and the top of the foundation wall.
👉🏻 Lightly hammer the stab tab of the DHB to hold the DHB in place against the mudsill.
👉🏻 Secure with Approved Fasteners*
👉🏻 Place sheathing on the hangers and nail-off.
*Check your local building code.
DROP SYSTEM®
Use the Dodge Hanger Corner® 1.5 (DHC15) along with the Dodge Hanger Top Leveler®(DHTL15) or Dodge Hanger Rear® (DHR) to install the starter row of the sheathing with a drop below the mudsill.
Select the DHC15 and the DHTL with saddle widths that fit the thickness of the sheathing material to be installed.
👉🏻 You will need a DHC15 for each outside corner.
👉🏻 Bend the top tab of the DHC15 over and place on the mudsill at each corner. If mudsill is larger than 1.5”, do not bend the top tab over, but attach directly to the side of the mudsill.
👉🏻 Lightly hammer the stab tab on the DHC15 to help hold it on the mudsill.
👉🏻 Fasten to the mudsill with Approved Fasteners*.
👉🏻 Using the DHC15 along with the DHTL , your sheathing will hang approximately 1” below the foundation.
👉🏻 Once your DHC15’s are installed, it is recommended you attach the DHTL is on a 1’ by 3’ pattern around the mud sill plate, after establishing the layout of the sheathing to be installed. You should place a DHTL no more than 6” in from each joint/seam.
👉🏻 For vertically installed sheathing (4’ x 8’, 9’, 10’, 12’) it is recommended you use (2) DHTL’s per sheet.
👉🏻 For horizontally installed wall sheathing (8’ x 4’) it is recommended you use (3) DHTL’s per sheet (i.e., (1) hanger each at 6”, 4’, 7’6”)
👉🏻 Bend the top tab of the DHTL over, forming a 90° angle, and set it on the top of the mudsill.
👉🏻 Lightly hammer the stab tab on the DHTL into the mudsill.
👉🏻 Attach with Approved Fasteners*.
👉🏻 The saddle of the DHTL will hang approximately 1” below the mudsill, allowing the sheathing to drop as it rests on the hanger.
🚫 If you can’t access the top of the mudsill, use the DHR.
✔ Insert the rear tab of the DHR between the mudsill and the top of the foundation wall.
✔ Lightly hammer the stab tab of the DHR to hold it in place against the mudsill.
✔ Place sheathing on the hangers and nail-off.
HOW TO INSTALL SHEATHING VIDEOS
🔨 How To Install Sheathing Without A Drop
🔨 How To Install Sheathing With A Drop